Hazelden Generator

Parsons’ scope of work for the Hazelden Generator project included the replacement of an existing 1000KW generator with a new 1000KW generator, the upgrade of an existing 600KW generator, the installation of new paralleling gear to parallel generators, and the installation of control systems to both generators with Integration to Building Management System (BMS.) In addition, Parsons replaced the existing step-up transformer with a new 2000KVA transformer. Parsons managed the electrical design of the entire project and saved the owner a total of $49,000.